Exhibit
No.
|
Description
|
Iris Energy Limited, November 2022 Monthly Investor Update, dated December 13, 2022
|
Iris Energy Limited
|
||
Date: December 13, 2022
|
By:
|
/s/ Daniel Roberts
|
Daniel Roberts
|
||
Co-Chief Executive Officer and Director
|
Key metrics2
|
Nov-22
|
|
Average operating hashrate (PH/s)
|
1,445
|
|
Bitcoin mined
|
151
|
|
Mining revenue (US$’000)
|
2,871
|
|
Electricity costs (US$’000)
|
1,905
|
|
Revenue per Bitcoin (US$)
|
18,955
|
|
Electricity costs per Bitcoin (US$)
|
12,581 (10,168 adj)3
|
• |
Corporate:
|
• |
On December 6, the Company provided an investor update – “Everything changes, everything remains the same” – in respect of its positioning, go-forward opportunities, and strategic priorities
|
o |
Risk-focused approach positions the Company to weather the storm and capitalize on the next bull run
|
o |
Liquidity (as of month end)
|
▪ |
$47 million cash, no debt4
|
▪ |
$21 million estimated net capex spend to achieve 180MW5
|
▪ |
$75 million remaining Bitmain prepayments
|
▪ |
$100 million unutilized under B. Riley equity facility6
|
▪ |
Potential monetization of assets through miner sales (2.4 EH/s down to 2.0 EH/s7)
|
o |
Opportunities
|
▪ |
Significant optionality from 180MW real assets platform (e.g. self-mining or hosting)
|
▪ |
Focus on expanding self-mining capacity to 5.4 EH/s
|
▪ |
Potential additional expansion from 20MW to 600MW at Childress
|
• |
On November 21, the Company also provided a corporate update and announced certain preliminary financial information and operational updates for Q1 FY23 and October 2022
|
• |
Operations (for the month of November 2022):
|
• |
Average operating hashrate of 1,445 PH/s (-63% vs. October)8
|
• |
Monthly operating revenue of $2.9 million (-67% vs. October)
|
• |
151 Bitcoin mined (-66% vs. October)
|
• |
Construction:
|
• |
Mackenzie (80MW – BC, Canada)
|
o |
Expansion from 50MW to 80MW energized on December 6, 2022, three weeks ahead of schedule
|
o |
Internal data center fit-out complete for the additional 30MW
|
• |
Childress (20MW – Texas, USA)
|
o |
Foundations and earthworks for the substation and first data center building (20MW) complete
|
o |
Structural steel for the first data center building (20MW) erected
|
o |
Substation area prepared for upcoming delivery and installation of the 600MW transformer and main power transformers
|
• |
Risk-focused approach positions the Company to weather the storm and capitalize on the next bull run
|
• |
Liquidity (as of month end)
|
• |
$47 million cash, no debt4
|
• |
$21 million estimated net capex spend to achieve 180MW5
|
• |
$75 million remaining Bitmain prepayments
|
• |
$100 million unutilized under B. Riley equity facility6
|
• |
Potential monetization of assets through miner sales (2.4 EH/s down to 2.0 EH/s7)
|
• |
Opportunities
|
• |
Significant optionality from 180MW real assets platform (e.g. self-mining or hosting)
|
• |
Focus on expanding self-mining capacity to 5.4 EH/s
|
• |
Potential additional expansion from 20MW to 600MW at Childress
|
|
|
|||
Childress – aerial view of completed foundations
and erection of structural steel for the first data
center building (20MW)
|
Childress – aerial view of the construction of the
600MW substation and first data center building
(20MW)
|
Canal Flats – Windermere Valley Saddle Club
awards ceremony
|
Operating
|
Sep-22
|
Oct-22
|
Nov-22
|
|
Renewable energy usage (MW)12*
|
84
|
123
|
46
|
|
Avg operating hashrate (PH/s)8*
|
2,679
|
3,899
|
1,445
|
Financial (unaudited)2
|
Sep-22
|
Oct-22
|
Nov-22
|
|
Bitcoin mined
|
325
|
448
|
151
|
|
Mining revenue (US$’000)
|
6,224
|
8,785
|
2,871
|
|
Electricity costs (US$’000)8*
|
2,737
|
4,167
|
1,905
|
|
Revenue per Bitcoin (US$)
|
19,124
|
19,591
|
18,955
|
|
Electricity costs per Bitcoin (US$)8*
|
8,410
|
9,293
|
12,581 (10,128 adj)3
|
2022
|
Jan
|
Feb
|
Mar
|
Apr
|
May
|
Jun
|
Jul
|
Aug
|
Sep
|
Oct
|
Nov
|
|
Avg operating
hashrate (PH/s)
– restated
|
802
|
844
|
849
|
1,028
|
1,165
|
1,164
|
1,120
|
2,162
|
2,679
|
3,899
|
1,445
|
|
BTC mined
– unchanged
|
126
|
110
|
121
|
137
|
151
|
148
|
154
|
301
|
325
|
448
|
151*
|
Hardware
|
Units
|
EH/s
(incremental)
|
EH/s
(cumulative)
|
||
Operating (as of December 12)**
|
S19j Pro13
|
12,042
|
1.1
|
1.1
|
|
Inventory – in transit and/or pending deployment***
|
S19j Pro14
|
9,223
|
0.9
|
0.9
|
|
Total
|
21,265
|
2.0
|
2.0
|
Site
|
Capacity
(MW)
|
Capacity
(EH/s)15
|
Timing
|
Status
|
|
Canal Flats (BC, Canada)
|
30
|
0.8
|
Complete
|
Operating
|
|
Mackenzie (BC, Canada)
|
50
|
1.5
|
Complete
|
Operating
|
|
30
|
1.0
|
Complete
|
Energized
|
||
Prince George (BC, Canada)
|
50
|
1.4
|
Complete
|
Operating
|
|
Total (BC, Canada)
|
160
|
4.7
|
|||
Childress (Texas, US)
|
20
|
0.7
|
2023
|
Under construction16
|
|
Total (Canada & USA)
|
180
|
5.4
|
• |
100% renewables: Iris Energy targets markets with low-cost, under-utilized renewable energy, and where the Company can support local communities
|
• |
Long-term security over infrastructure, land and power supply: Iris Energy builds, owns and operates its electrical infrastructure and proprietary data centers, providing
long-term security and operational control over its assets
|
• |
Seasoned management team: Iris Energy’s team has an impressive track record of success across energy, infrastructure, renewables, finance, digital assets and data centers
with cumulative experience in delivering >$25bn in energy and infrastructure projects globally
|