Exhibit
No. |
Description
|
|
Iris Energy Limited, September 2022 Monthly Investor Update, dated October 7, 2022
|
Iris Energy Limited
|
||
Date: October 7, 2022
|
By:
|
/s/ Daniel Roberts
|
Daniel Roberts
|
||
Co-Chief Executive Officer and Director
|
Key metrics
|
Sep-22
|
|
Average operating hashrate (PH/s)
|
2,729
|
|
Bitcoin mined2
|
325
|
|
Mining revenue (US$’000)
|
6,224
|
|
Electricity costs (US$’000)
|
2,829
|
|
Revenue per Bitcoin (US$)
|
19,124
|
|
Electricity costs per Bitcoin (US$)
|
8,691
|
• |
Corporate:
|
• |
Company’s third operating site, Prince George (50MW), was energized on schedule, increasing total Company operating capacity by >60% to exceed 3.7 EH/s
|
• |
Mackenzie expansion from 50MW to 80MW remains on track to be energized by end of Q4 2022, increasing expected near-term operating capacity to 4.7 EH/s
|
• |
Initial 40MW planned at Childress to reach 6.0 EH/s
|
• |
Reported record full year FY22 results
|
• |
Operations:
|
• |
Average operating hashrate of 2,729 PH/s (+24% vs. August)
|
• |
Monthly operating revenue of US$6.2 million (-6% vs. August)
|
• |
325 Bitcoin mined (+8% vs. August)
|
• |
Construction:
|
• |
Mackenzie (2.5 EH/s, 80MW – BC, Canada)
|
o |
Expansion from 50MW to 80MW on track for energization by the end Q4 2022
|
o |
Internal fit-out of the remaining 10MW of the third data center building progressing
|
o |
Foundations complete and erection of structural steel has commenced for the fourth data center building (20MW)
|
• |
Childress (1.3 EH/s, 40MW – Texas, USA)
|
o |
An initial 40MW development is planned at the 600MW site
|
o |
Earthworks continued and foundation preparation commenced for the substation area and first data center building (20MW)
|
o |
Key civil, data center building and substation contractors mobilized on site
|
|
||||
Mackenzie – concrete slab pour at the fourth data center building (20MW)
|
Mackenzie – erection of structural steel at the fourth data center building (20MW)
|
|
||||
Prince George – technicians energizing ASICs during commissioning
|
Prince George – fully commissioned
|
|
||||
Childress – aerial view of the warehouse, substation and data center areas
|
Childress – aerial view of substation foundation preparations
|
Operating*
|
Jul-22
|
Aug-22
|
Sep-22
|
||
Renewable energy usage (MW)5
|
36
|
69
|
85
|
||
Avg operating hashrate (PH/s)
|
1,117
|
2,204
|
2,729
|
Financial (unaudited)
|
Jul-22
|
Aug-22
|
Sep-22
|
||
Bitcoin mined*
|
154
|
301
|
325
|
||
Mining revenue (US$’000)
|
3,358
|
6,629
|
6,224
|
||
Electricity costs (US$’000)
|
1,360
|
2,436
|
2,829
|
||
Revenue per Bitcoin (US$)
|
21,823
|
22,027
|
19,124
|
||
Electricity costs per Bitcoin (US$)
|
8,836
|
8,094
|
8,691
|
Miner Shipping Schedule
|
Hardware
|
Units
|
EH/s
(incremental)
|
EH/s
(cumulative)
|
|
Operating (September 2022)
|
S19j Pro / S19j 6
|
27,244
|
2.7
|
2.7
|
|
Inventory – pending deployment
|
S19j Pro / S19j 7
|
18,248
|
1.6
|
4.3
|
|
Inventory – in transit
|
S19j Pro / S19j
|
14,754
|
1.4
|
5.7
|
|
Q4 2022
|
S19j
|
3,000
|
0.3
|
6.0
|
|
Total
|
63,246
|
6.0
|
6.0
|
Site
|
Capacity
(MW)
|
Capacity
(EH/s)
|
Timing
|
Status
|
|
Canal Flats (BC, Canada)
|
30
|
0.8
|
Complete
|
Operating
|
|
Mackenzie (BC, Canada)
|
50
|
1.5
|
Complete
|
Operating
|
|
30
|
1.0
|
Q4 2022
|
Under construction
|
||
Prince George (BC, Canada)
|
50
|
1.4
|
Complete
|
Operating
|
|
Total (end of Q4 2022)
|
160
|
4.7
|
|||
Childress (Texas, US)
|
40
|
1.3
|
2023
|
Under construction
|
|
Total (2023)
|
200
|
6.0
|
• |
100% renewables: Iris Energy targets markets with low-cost, under-utilized renewable energy, and where the Company can support local communities
|
• |
Long-term security over infrastructure, land and power supply: Iris Energy builds, owns and operates its electrical infrastructure and proprietary data centers, providing
long-term security and operational control over its assets
|
• |
Seasoned management team: Iris Energy’s team has an impressive track record of success across energy, infrastructure, renewables, finance, digital assets and data centers
with cumulative experience in delivering >$25bn in energy and infrastructure projects globally
|