Iris Energy Limited, August 2022 Monthly Investor Update, dated September 7, 2022
|
Iris Energy Limited
|
||
Date: September 7, 2022
|
By:
|
/s/ Daniel Roberts
|
Daniel Roberts
|
||
Co-Chief Executive Officer and Director
|
Key metrics
|
Aug-22
|
|
Average operating hashrate (PH/s)
|
2,204
|
|
Bitcoin mined2
|
301
|
|
Mining revenue (US$'000)
|
6,629
|
|
Electricity costs (US$'000)
|
2,436
|
|
Revenue per Bitcoin (US$)
|
22,027
|
|
Electricity costs per Bitcoin (US$)
|
8,094
|
• |
Corporate:
|
• |
Prince George (50MW) on track for energization in September 2022, increasing total expected Company operating capacity to 3.7 EH/s
|
• |
Company operating capacity guidance increased from 4.3 EH/s to 4.7 EH/s by the end of Q4 2022
|
• |
Company to publish its financial results for the full year ended June 30, 2022 on Tuesday, September 13, 2022 Eastern Time (conference call to be hosted at 5:00 p.m. USA Eastern Time)
|
• |
Operations:
|
• |
Average operating hashrate of 2,204 PH/s (+97% vs. July)
|
• |
Monthly operating revenue of US$6.6 million (+97% vs. July)
|
• |
301 Bitcoin mined (+96% vs. July)
|
• |
Construction:
|
• |
Mackenzie (2.5 EH/s, 80MW – BC, Canada)
|
o |
Construction activities continue to progress for expansion from 50MW to 80MW and remains on track to be completed by the end of Q4 2022
|
o |
Expected site operating capacity increased from 2.1 EH/s to 2.5 EH/s by the end of Q4 2022
|
• |
Prince George (1.4 EH/s, 50MW – BC, Canada)
|
o |
Commissioning activities underway, with major equipment installation in the substation close to complete
|
o |
Construction of all three data center buildings complete
|
o |
Internal fit out for the first and third data center buildings (20MW each) complete and well progressed for the second data center building (10MW)
|
o |
Construction of the high voltage connection to the BC Hydro transmission network complete
|
• |
Childress (1.3 EH/s, 40MW – Texas, USA)
|
o |
An initial 40MW development is planned at the 600MW site
|
o |
Earthworks have commenced for the substation area, the first data center building (20MW) area and internal road network
|
Webcast and Conference Details
|
||
Date:
|
Tuesday, September 13, 2022
|
|
Time:
|
5:00 p.m. USA Eastern Time (2:00 p.m. Pacific Time or 7:00 a.m. Australian Eastern Standard Time)
|
|
Participant
|
Registration Link
|
|
Live Webcast
|
Use this link
|
|
Phone Dial-In with Live Q&A
|
Use this link
|
Mackenzie – foundation works for the fourth data center building (20MW)
|
Mackenzie – celebrating commissioning of the first 50MW
|
Prince George – 69kV high voltage transformer being positioned
|
Prince George – substation construction progress
|
Childress – earthworks have commenced for the first data center building (20MW)
|
Childress – aerial view of site grading
|
Operating*
|
Jun-22
|
Jul-22
|
Aug-22
|
|
Renewable energy usage (MW)6
|
36
|
36
|
69
|
|
Avg operating hashrate (PH/s)
|
1,164
|
1,117
|
2,204
|
Financial (unaudited)
|
Jun-22
|
Jul-22
|
Aug-22
|
|
Bitcoin mined*
|
148
|
154
|
301
|
|
Mining revenue (US$’000)
|
3,546
|
3,358
|
6,629
|
|
Electricity costs (US$’000)
|
1,315
|
1,360**
|
2,436
|
|
Revenue per Bitcoin (US$)
|
23,925
|
21,823
|
22,027
|
|
Electricity costs per Bitcoin (US$)
|
8,875
|
8,836
|
8,094
|
Miner Shipping Schedule
|
Hardware
|
Units
|
EH/s
(incremental)
|
EH/s
(cumulative)
|
|
Operating (August 2022)
|
S19j Pro / S19j7
|
23,831
|
2.2
|
2.2
|
|
Inventory – pending deployment
|
S19j Pro / S19j8
|
16,956
|
1.6
|
3.8
|
|
Inventory – in transit
|
S19j Pro / S19j
|
3,608
|
0.4
|
4.2
|
|
Q3 2022
|
S19j Pro / S19j
|
17,296
|
1.7
|
5.9
|
|
Q4 2022
|
S19j
|
1,500
|
0.1
|
6.0
|
|
Total
|
63,191
|
6.0
|
6.0
|
Site
|
Capacity
(MW)
|
Capacity
(EH/s)
|
Timing
|
Status
|
|
Canal Flats (BC, Canada)
|
30
|
0.8
|
Complete
|
Operating
|
|
Mackenzie (BC, Canada)
|
50
|
1.5
|
Complete
|
Operating
|
|
30
|
1.09
|
Q4 2022
|
Under construction
|
||
Prince George (BC, Canada)
|
50
|
1.4
|
Q3 2022
|
Commissioning
|
|
Total (end of Q4 2022)
|
160
|
4.7
|
|||
Childress (Texas, US)
|
40
|
1.3
|
2023
|
Under construction
|
|
Total (2023)
|
200
|
6.0
|
• |
100% renewables: Iris Energy targets markets with low-cost, under-utilized renewable energy, and where the Company can support local communities
|
• |
Long-term security over infrastructure, land and power supply: Iris Energy builds, owns and operates its electrical infrastructure and proprietary data centers, providing long-term security and
operational control over its assets
|
• |
Seasoned management team: Iris Energy’s team has an impressive track record of success across energy, infrastructure, renewables, finance, digital assets and data centers with cumulative experience in
delivering >$25bn in energy and infrastructure projects globally
|