Iris Energy Limited, November 2021 Monthly Investor Update, dated December 9, 2021
|
Iris Energy Limited
|
||
Date: December 9, 2021
|
By:
|
/s/ Daniel Roberts
|
Daniel Roberts
|
||
Co-Chief Executive Officer and Director
|
|
• |
Successful completion of a $232 million Nasdaq IPO. J.P. Morgan, Canaccord Genuity and Citigroup acted as lead book-running managers.
|
• |
15.2 EH/s of miners secured1:
|
o |
0.7 EH/s currently operating
|
o |
0.8 EH/s to be shipped in 2021 (2,841 Bitmain S19j Pro miners currently in transit2; 2,290 Bitmain S19j Pro and 3,122 Bitmain S19j miners scheduled for December)
|
o |
5.7 EH/s to be shipped in 2022 (42,575 Bitmain S19j Pro and 15,705 Bitmain S19j miners)
|
o |
8.0 EH/s to be shipped in 2023 (80,294 Bitmain S19j Pro miners).
|
• |
Operations:
|
o |
657 PH/s average operating hashrate in November, powered by 98% renewable energy
|
o |
113 Bitcoin mined during the month, generating monthly operating revenue of $6.6 million
|
o |
Welcomed Lindsay Ward (President) and Mike Alfred (Non-Executive Director).
|
• |
Construction & Development:
|
o |
Construction continues to progress at Mackenzie (BC, Canada), expected to deliver capacity of 1.5 EH/s (50MW) in 2022
|
o |
Broke ground at Prince George (BC, Canada), expected to deliver capacity of 1.4 EH/s (50MW) in 2022 and expansion to 2.4 EH/s (85MW) in 2023
|
o |
Development works continued on a range of additional sites which have been secured across Canada, USA and Asia-Pacific. Development of those sites is expected to support up to 1GW of aggregate power capacity to install the Company’s 15.2
EH/s of miners (~530MW).
|
• |
Lindsay has over 35 years’ operational experience in front-line senior business leadership positions as Chief Executive Officer, Managing Director and General Manager in the infrastructure, industrials, energy and resources industries.
Lindsay’s experience spans a vast range of operational and greenfield expansion projects across gas pipelines, wind farms, solar farms, ports, rail, bulk liquid storage terminals and conventional energy generation assets.
|
• |
Mike is a private investor, advisor and board member, and previously served as the CEO of Digital Assets Data, Inc., a financial technology and data company building enterprise-grade software and data feeds for the digital asset ecosystem,
from when he co-founded the company in January 2018 through its sale to New York Digital Investment Group LLC (NYDIG) in November 2020.
|
Operating*
|
Sep-21
|
Oct-21
|
Nov-21
|
|
Operating power usage (MW)
|
19
|
22
|
23
|
|
Avg operating hashrate (PH/s)
|
549
|
649
|
657
|
Financial (unaudited)
|
Sep-21
|
Oct-21
|
Nov-21
|
|
Bitcoin mined
|
113
|
127
|
113
|
|
Mining revenue (US$’000)3
|
5,087
|
7,338
|
6,593
|
|
Electricity costs (US$’000)3
|
737
|
852
|
822
|
|
Revenue per Bitcoin (US$)
|
44,847
|
57,634
|
58,328
|
|
Electricity costs per Bitcoin (US$)
|
6,498
|
6,695
|
7,275
|
Miner Shipping Schedule
|
Hardware
|
Units
|
PH/s (shipments)
|
PH/s
(cumulative)
|
Operating (November 2021)
|
S19j Pro / A124
|
7,770
|
657
|
657
|
Q4 2021
|
S19j Pro / S19j
|
8,253
|
795
|
1,452
|
Q1 2022
|
S19j Pro / S19j
|
11,584
|
1,112
|
2,564
|
Q2 2022
|
S19j Pro / S19j
|
11,660
|
1,119
|
3,683
|
Q3 2022
|
S19j Pro / S19j
|
7,063
|
659
|
4,342
|
Q4 2022
|
S19j Pro / S19j
|
27,973
|
2,781
|
7,123
|
Q1 2023
|
S19j Pro
|
26,577
|
2,658
|
9,781
|
Q2 2023
|
S19j Pro
|
26,765
|
2,676
|
12,457
|
Q3 2023
|
S19j Pro
|
26,952
|
2,695
|
15,152
|
Total
|
154,597
|
15,152
|
Site Overview
|
Capacity (MW)
|
Capacity (EH/s)
|
Timing
|
Status
|
Canal Flats
|
30
|
0.7
|
Complete
|
Operating
|
Mackenzie
|
50
|
1.5
|
Q2-Q3 2022
|
Under construction
|
Prince George
|
85
|
2.4
|
Q3 2022/2023
|
Under construction
|
Other secured sites
|
365
|
10.6
|
TBC
|
Under development
|
Total
|
530
|
15.2
|
|