Iris Energy Doubles Operating Capacity to >2.3 EH/s
Iris Energy Doubles Operating Capacity to >2.3 EH/s
Deployment Options Underway for 6.0 EH/s
The Company recently energized the remainder of the first 1.5 EH/s (50MW) at its second operating site in
- Phase one: 0.3 EH/s (9MW) –
April 13, 2022 (original target end of Q2 2022) - Phase two: 1.2 EH/s (41MW) –
August 5, 2022 (original target end of Q3 2022)
The Company’s next site, in
In addition:
- The Company continues to work through deployment options for its remaining 2.3 EH/s of miners, including the recently announced 1.7 EH/s of Bitmain S19j Pro miners to be shipped in
August 2022 , increasing expected operating capacity to 6.0 EH/s $46.7 million of the previous$130 million of payments made to Bitmain have been applied to secure the additional 1.7 EH/s, and utilization of the remaining$83.3 million of payments in respect of additional contracted miners above the 6.0 EH/s continue to be subject to ongoing discussions with Bitmain1
Iris Energy’s Co-Founder & Co-CEO,
“The delivery of
About
- Focus on low-cost renewables:
Iris Energy targets markets with low-cost, excess and/or under-utilized renewable energy, and where the Company can support local communities - Long-term security over infrastructure, land and power supply:
Iris Energy builds, owns and operates its electrical infrastructure and proprietary data centers, providing long-term security and operational control over its assets - Seasoned management team: Iris Energy’s team has an impressive track record of success across energy, infrastructure, renewables, finance, digital assets and data centers with cumulative experience in delivering >
$25bn in energy and infrastructure projects globally
Forward-Looking Statements
This press release includes “forward-looking statements” within the meaning of the Private Securities Litigation Reform Act of 1995. Forward-looking statements generally relate to future events or Iris Energy’s future financial or operating performance. For example, forward-looking statements include but are not limited to the expected increase in the Company’s power capacity and operating capacity, the Company’s business plan, the Company’s capital raising plans, the Company’s anticipated capital expenditures and additional borrowings, the impact of discussions with Bitmain regarding the Company’s hardware purchase contract for additional miners, and the expected schedule for hardware deliveries and for commencing and/or expanding operations at the Company’s sites. In some cases, you can identify forward-looking statements by terminology such as “anticipate,” “believe,” “may,” “can,” “should,” “could,” “might,” “plan,” “possible,” “project,” “strive,” “budget,” “forecast,” “expect,” “intend,” “target”, “will,” “estimate,” “predict,” “potential,” “continue,” “scheduled” or the negatives of these terms or variations of them or similar terminology, but the absence of these words does not mean that statement is not forward-looking. Such forward-looking statements are subject to risks, uncertainties, and other factors which could cause actual results to differ materially from those expressed or implied by such forward looking statements. In addition, any statements or information that refer to expectations, beliefs, plans, projections, objectives, performance or other characterizations of future events or circumstances, including any underlying assumptions, are forward-looking.
These forward-looking statements are based on management’s current expectations and beliefs. These statements are neither promises nor guarantees, but involve known and unknown risks, uncertainties and other important factors that may cause Iris Energy’s actual results, performance or achievements to be materially different from any future results, performance or achievements expressed or implied by the forward-looking statements, including, but not limited to: Iris Energy’s limited operating history with operating losses; electricity outage, limitation of electricity supply or increase in electricity costs; long term outage or limitation of the internet connection at Iris Energy’s sites; any critical failure of key electrical or data center equipment; serial defects or underperformance with respect to Iris Energy’s equipment; failure of suppliers to perform under the relevant supply contracts for equipment that has already been procured which may delay Iris Energy’s expansion plans; supply chain and logistics issues for
These and other important factors could cause actual results to differ materially from those indicated by the forward-looking statements made in this press release. Any forward-looking statement that
Contacts
Media
Domestique
+61 477 946 068
Investors
Bom Shin
+61 411 376 332
bom.shin@irisenergy.co
To keep updated on Iris Energy’s news releases and
_____________________________
1 The timing and volume of any additional future deliveries (i.e. beyond the 1.7 EH/s scheduled for shipment in

Source: IRIS ENERGY LIMITED